Hub City Times

  • News
    • Around the County
    • Arts & Ent
    • Education
    • Government
    • Local
  • Covid 19
  • Opinion
  • Sports
    • Sports News
    • High School Sports Scores
    • Wisconsin Rapids Rafters
  • Coming Events
  • Business
  • Obits
  • Classifieds
    • Place Ad
    • View Ads
  • Legal Ads
    • Our Legals
    • Statewide
  • Senior Photos 2021
Local
Home›News›Local›Plans presented for major Maple Avenue reconstruction

Plans presented for major Maple Avenue reconstruction

By Hub City Times
February 13, 2015
1385
0
Share:
Maple Avenue Reconstruction marshfield Tom Turchi

Similar to the work done on Chestnut Avenue in 2013, the city looks to begin construction this spring


By Adam Hocking

Editor

MARSHFIELD — City officials held a public information session Monday night to inform residents about the upcoming construction project that will span Maple Avenue, running from Veterans Parkway to Sixth Street.

Segments of Third, Fourth, Fifth, and a portion of Sixth Street will also undergo major construction between Maple and Central Avenues. Second Street was initially included in the construction plans but also has been targeted as a potential area to add green space to downtown Marshfield as part of the city’s long-term vision.

“We’re putting a hold on Second Street between Central and Maple because there’s been a downtown master plan that has come out now that’s showing a green corridor between the Library and (Steve J. Miller) Park, so at this point we are going to build the project without Second Street until that issue gets discussed and worked through,” said City Engineer Tom Turchi.

Project planners compared the work that will be done to the construction completed on Chestnut Avenue and side streets in 2013. Turchi estimated the total project cost at about $2.8 million and said he viewed the project as long overdue considering the age of the some the utilities the city will be replacing.

“This reconstruction project is going to take care of all the underground utilities, so there’s locations where we’re redoing the sanitary sewer main that’s in excess of 100 years old. There’s locations that the water main is being replaced. The storm sewer we figured is over 85 years old, and that’s all beyond its life span, so in this instance we’re basically reconstructing all the underground utilities as well as reconstructing and building a brand new street,” Turchi said.

All of the streets and sidewalks in the construction zone will also be redone.

While the scope of the work being done will be significant, the city will complete the project in stages to minimize impact on business and property owners. The city will ensure access to municipal parking lots in the construction zone throughout the project.

The Board of Public Works will give final approval to the construction plans on Monday, Feb. 16. The city will start considering bids for the project on March 16 and is targeting a construction start date of May 4.

Turchi said that per state statutes, the city must choose the “lowest responsible bidder” for the project. He added that the city has pre-qualification requirements for any contractor to bid on the project.

“They have to show that they have enough financial ability and enough equipment to do the project, and then that gets approved by the Board of Public Works,” Turchi said. “Based upon that, anyone that then is prequalified can bid on the project, and the lowest responsible bidder is the one we have to award it to, so we don’t go out and pick a specific contractor, one over another.”

The city hopes to complete construction by the end of October this year.

Tagsbuilding projectsconstructionDepartment of Public WorksdowntownFeaturedMaple AvenueMaple Avenue ReconstructionPublic InformationTom Turchi
Previous Article

MAPS accepts pet supplies donation from Festival ...

Next Article

Shirley’s House of Hope kicks off capital ...

0
Shares
  • 0
  • +
  • 0
  • 0
  • 0
  • 0

Related articles More from author

  • LocalNews

    Marshfield man struck by train

    July 30, 2014
    By Hub City Times
  • Photo Gallery

    Photos from Relay For Life in Marshfield

    August 2, 2014
    By HubCityAdmin
  • News

    Cancer gets lapped at Relay For Life

    August 2, 2014
    By Hub City Times
  • Business

    Hotel Marshfield combines sophistication with comfort

    August 6, 2014
    By Hub City Times
  • Arts & Entertainment

    New Visions Gallery fundraises in style

    August 8, 2014
    By Hub City Times
  • BusinessFood

    Marshfield Farmers’ Market in full bloom

    August 9, 2014
    By Hub City Times

Leave a reply Cancel reply

You must be logged in to post a comment.

About Us


Hub City Times is published by Multi Media Channels LLC, N2919 County Road QQ Waupaca, WI 54981.

Copyright © 2020 Multi Media Channels, All Rights Reserved. Designed by MMC Team Awesome
×